Runway Resurfacing

Elevating Aviation Standards: the resurfacing of 3.350km main runway at Malta International Airport's.
Runway Resurfacing
  • Project Type
    Aviation & Infrastructure
  • Location
    Malta
  • Services
    Design + Engineering + Management
  • Value
    20-50 mil
  • Status
    Completed 2008

Providing specialist consultancy to Malta International Airport plc during the design, analysis and implementation stages for the resurfacing of the main runway (Runway 13-31), along a total length of circa 3.350km. The project entailed the scarification and reinstatement of 50mm thickness of the existing asphalt along 15-metre central width (keel section) of the runway (7.5m on either side of the centreline), whilst a 60mm thick intervention on a width of 30-metres was carried out on the touch-down area (on Threshold 31).